Case Study · Rock Stabilisation

Aira Force Waterfall, Cumbria

A complex rock stabilisation project delivered in a steep heritage gorge while keeping this popular National Trust attraction open to visitors.

Aira Force rock stabilisation works
ClientNational Trust / ARUP
ConsultantKeyGS
LocationAira Force, Cumbria
CompletedMay 2023
ProgrammePublic access maintained
Project overview

Protecting a landmark waterfall and its visitors

Aira Force presented unstable rock above visitor paths and viewing areas within a steep, wooded gorge. Restricted access, continuous public use and the heritage setting demanded a carefully controlled solution.

D-GEO combined IRATA rope access, rock scaling, high-yield anchors, lacing cables and mesh installation, with associated tree, steelwork and heritage reinstatement works.

01 · The challenge

Steep gorge access and live visitor routes

  • Unstable rock above paths and viewing areas
  • Steep, wooded gorge with difficult access
  • Heritage masonry and landscape constraints
  • Public access maintained throughout
02 · The solution

Targeted rock support in a sensitive setting

IRATA rope-access teams installed high-yield GEWI anchors, galvanised lacing cables and Maccaferri DT mesh. The package also included controlled tree works, structural steel and handrail repairs, and careful reinstatement of heritage masonry and flags.

  • Type 3 testing verified the anchor system
  • Sequenced exclusion zones protected visitors
  • Heritage features were retained and reinstated
84m rock anchors
180m²Maccaferri DT mesh
9Lacing cables
OpenThroughout the works
03 · Scope of works

How the project was delivered

01

Site establishment

Visitor controls, access systems and exclusion zones.

02

Tree and vegetation works

Selective clearance and controlled removal in the gorge.

03

Anchors and testing

Type 3 testing and installation of high-yield GEWI anchors.

04

Lacing cables

Galvanised cables installed to secure the rock mass.

05

Rock scaling and mesh

Scaling followed by approximately 180m² of DT mesh.

06

Heritage reinstatement

Handrails, structural steel, masonry and flags completed.

04 · Outcome

Long-term safety with the visitor experience protected

The completed scheme secured the rock face and improved long-term visitor safety while protecting the character of Aira Force. The attraction remained open, and the work was delivered safely, on programme and within budget.

Project gallery

Works and completed installation