Cloud Hill Quarry, Derbyshire
A major two-phase stabilisation scheme above a primary crusher, delivered safely in an active quarry without interrupting operations.

Stabilising a critical active-quarry slope
The slope stood directly above Cloud Hill Quarry’s primary crusher, making stability essential to safety and production. Steep terrain, variable ground and continuous quarry operations shaped every stage of delivery.
D-GEO delivered soil nailing and three complementary mesh systems using a long-reach excavator drill, suspended rigs and IRATA rope-access teams.
Working above critical quarry infrastructure
- Active quarry and primary crusher below
- Variable upper and lower slope conditions
- Restricted access for drilling and materials
- Production needed to continue throughout
Two-phase anchoring and tailored mesh systems
Phase one installed 140 R32 anchors at 4.5m; phase two added 60 R32 anchors at 7.5m, with crest and local rock anchors. MacMat R, TECCO G65/3 and Maccaferri rockface mesh were matched to the differing ground conditions.
- Long-reach and suspended drilling reached the full slope
- IRATA teams controlled installation above the crusher
- Quarry operations continued during the works
How the project was delivered
Site establishment
Work zones and controls coordinated with live quarry operations.
Slope preparation
Scaling, preparation and access establishment across the face.
Phase-one drilling
140 R32 anchors installed to 4.5m using specialist plant.
Phase-two soil nailing
60 R32 anchors installed to 7.5m, plus 35 crest anchors.
Multi-system mesh
MacMat R, TECCO G65/3 and rockface mesh installed by zone.
Inspection and handover
Final tensioning, inspection and coordinated clean handover.
Critical infrastructure protected without lost production
The completed scheme provides durable protection to the primary crusher and active work areas below. Delivery finished on time and under budget while quarry operations were maintained.
Works and completed installation