Case Study · Slope Stabilisation

Cloud Hill Quarry, Derbyshire

A major two-phase stabilisation scheme above a primary crusher, delivered safely in an active quarry without interrupting operations.

Cloud Hill Quarry slope stabilisation works
ClientBreedon Group
ConsultantNovaGeo Consulting Ltd
LocationCloud Hill Quarry, Derbyshire
Completed29 August 2025
ProgrammeOn time / under budget
Project overview

Stabilising a critical active-quarry slope

The slope stood directly above Cloud Hill Quarry’s primary crusher, making stability essential to safety and production. Steep terrain, variable ground and continuous quarry operations shaped every stage of delivery.

D-GEO delivered soil nailing and three complementary mesh systems using a long-reach excavator drill, suspended rigs and IRATA rope-access teams.

01 · The challenge

Working above critical quarry infrastructure

  • Active quarry and primary crusher below
  • Variable upper and lower slope conditions
  • Restricted access for drilling and materials
  • Production needed to continue throughout
02 · The solution

Two-phase anchoring and tailored mesh systems

Phase one installed 140 R32 anchors at 4.5m; phase two added 60 R32 anchors at 7.5m, with crest and local rock anchors. MacMat R, TECCO G65/3 and Maccaferri rockface mesh were matched to the differing ground conditions.

  • Long-reach and suspended drilling reached the full slope
  • IRATA teams controlled installation above the crusher
  • Quarry operations continued during the works
200R32 soil nails
2,885m²Total mesh coverage
7.5mMaximum anchor depth
On timeAnd under budget
03 · Scope of works

How the project was delivered

01

Site establishment

Work zones and controls coordinated with live quarry operations.

02

Slope preparation

Scaling, preparation and access establishment across the face.

03

Phase-one drilling

140 R32 anchors installed to 4.5m using specialist plant.

04

Phase-two soil nailing

60 R32 anchors installed to 7.5m, plus 35 crest anchors.

05

Multi-system mesh

MacMat R, TECCO G65/3 and rockface mesh installed by zone.

06

Inspection and handover

Final tensioning, inspection and coordinated clean handover.

04 · Outcome

Critical infrastructure protected without lost production

The completed scheme provides durable protection to the primary crusher and active work areas below. Delivery finished on time and under budget while quarry operations were maintained.

Project gallery

Works and completed installation