Case Study · Slope Stabilisation

Castle Walk, Bridgnorth

A technically challenging public-facing slope stabilisation scheme delivered safely, on time and within budget.

Castle Walk slope stabilisation works
ClientBridgnorth Town Council
ConsultantNova Geo Consulting
LocationBridgnorth
CompletedNovember 2025
Programme12 weeks
Project overview

Protecting a sensitive public location

Castle Walk presented a steep slope above public walkways and neighbouring properties. Restricted access, ongoing public use and the visual character of the site demanded a robust engineered solution with minimal disruption.

D-GEO stabilised the slope, reinforced the existing retaining wall and reinstated vegetation to create a durable and visually sympathetic finish.

01 · The challenge

Complex access and public safety

  • Steep slope above public routes
  • Restricted drilling and material access
  • Existing retaining wall requiring reinforcement
  • Nearby businesses and properties
02 · The solution

Engineered stability with a sensitive finish

IRATA rope access and lightweight drilling reduced the need for heavy plant. Works combined de-vegetation, testing, soil nailing, reinforced mesh and carefully planned vegetation reinstatement.

  • Controlled work zones maintained public safety
  • Testing verified the designed anchor system
  • Low-maintenance erosion control supported regrowth
205R32 soil nails
850m²Maccaferri mesh
600Vinca minor plants
12Week programme
03 · Scope of works

How the project was delivered

01

Site establishment

Secure access, compound and exclusion zones.

02

Slope preparation

Controlled de-vegetation and debris management.

03

Testing and drilling

Suitability testing and lightweight drilling.

04

Soil nailing

Installation to the engineered layout.

05

Mesh installation

Reinforced stability and erosion control.

06

Reinstatement

Planting, inspections and clean handover.

04 · Outcome

Safer, stable and sympathetically restored

The scheme improved long-term slope stability and public safety while maintaining access and limiting disruption. Engineered reinforcement was integrated with low-maintenance vegetation to preserve the character of Castle Walk.

Project gallery

Works and completed installation

Discuss your project

Planning works in a difficult-access location?

Talk to D-GEO about the site, constraints and outcome you need.