Case Study · Mine Ground Support

Birkshead Mine, Cumbria

Critical roof and wall support delivered safely above live plant in an operational mine.

Birkshead Mine ground support works
ClientSaint-Gobain
ConsultantSaint-Gobain Geotechnical Team
LocationAppleby-in-Westmorland, Cumbria
Completed14 March 2025
Programme46 shifts
Project overview

Reinforcing a live operational mine

Unsupported roof and wall spans above the Hazemag installation created potential falling-ground hazards. The works required precise geotechnical installation above live plant while maintaining safe mine access.

D-GEO installed overlapping RBHB5 mesh panels and fully encapsulated M24 AT roof bolts to Saint-Gobain’s verified geotechnical layout.

01 · The challenge

Overhead work in an operational mine

  • Unsupported roof and wall spans
  • Live Hazemag plant below the work area
  • Restricted underground access
  • Precise mesh coverage and bolt spacing
02 · The solution

Uniform, fully encapsulated ground support

A 40-metre, five-lift scaffold created safe access above the plant. Mesh panel installation and resin-encapsulated roof bolting were phased to maintain operations, with complete drilling and anchor records for client verification.

  • Weekly inspected and tagged scaffold access
  • Phased working maintained operational access
  • Additional bolts reinforced the main roof beam
686M24 AT roof bolts
1,000m²Roof and wall coverage
250RBHB5 mesh panels
46Incident-free shifts
03 · Scope of works

How the project was delivered

01

Scaffold establishment

40-metre, five-lift access scaffold with exclusion zones.

02

Layout verification

Bolt locations confirmed by the geotechnical representative.

03

Drilling and resin installation

Bolt holes drilled and resin capsules installed for full encapsulation.

04

Roof bolt installation

686 M24 AT bolts installed at designed centres.

05

Mesh panel installation

250 overlapping RBHB5 panels secured with plates and nuts.

06

Snagging and handover

Coverage adjusted, surplus materials removed and works signed off.

04 · Outcome

Long-term protection above critical plant

The completed installation provides uniform load transfer across the mine roof and walls, reducing rockfall risk above the Hazemag area. The project achieved client sign-off, programme completion and zero safety incidents across 46 shifts.

Project gallery

Works and completed installation